Contact Us | Our Company | Careers | Site Map  

 

At Multifilm, we use a relatively large amount of cooling capacity in our extruders and printing presses, and in late 2008, we realized that our chillers were in need of replacement. Environmental responsibility is important to Multifilm, and we decided to explore using geothermal energy for our machinery cooling needs, as well as heating and air-conditioning our plant. 

The concept is fairly simple; use groundwater from the underground reservoir or aquifer, which is always at a constant temperature of around 52°F to cool our plant in the summer and cool the machinery all year round, and use the waste heat from our processes to heat the plant in winter. We pump water from the ground to power our AC system and cool our cast film extrusion lines and CI drums for our presses.

By using a closed-loop system, whereby the same water we abstract from the ground is returned to the ground having passed through a series of heat exchangers, the water is returned untouched by any process before it returns to the aquifer. The project not only reduces Multifilm's carbon footprint by ensuring the plant consumes less energy, but also saves us more than 25% of our annual electricity costs.

All of this is being described in a document which is to be produced monthly – as Multifilm’s ‘Carbon Statement’ and an example of the format of this document will be made available shortly.

 

Below is a "photo-blog" of the progress on the installation of the geothermal system.
 

 

Clive Maidment, our project manager and
energy consultant presents the finalized
plan to our team in April 2009.

Clive is a consultant that specializes in energy-saving projects. He can be reached
via email at clive@maidment.eu

Well drilling commenced in May 2009.
We will use water from seven separate wells in two locations.

 

Close-up of the drilling. The water is down at 300 feet, and the Midwest soil is ideal for this type of application.

Supply and rejection lines are piped in
under the floor.

Supply and rejection lines are brought into the building in October 2009.

The heat exchangers and the control panel will go in the space to the left.

Halfway done! The three supply lines from
the wells are in place.

January 2010, the copper piping arrives that will distribute the water throughout the plant.

Hundreds of yards of copper pipes to transport the water around the plant are mounted in
the ceiling by our contactor team.

The pipes connect to air-handlers that are lined with coils and fans that will blow cold or hot air around the plant.

February 2010, rejection and supply lines are in place and the floor is filled back up.

Pressure valves are temporary placed on the supply lines to make sure we have enough water flow to handle our needs.

February 18, 2010, the pump motors arrived today...

...as did the heat exchangers!

Now starts the real challenge: connecting
the giant puzzle of pipes, pumps, heat-
exchangers and controllers!

March 4th, the first copper pipes are attached.

Slowly making progress.

March 10th, the pumps are connected.

Mid-March, the control panel has arrived and is put in place.

 

March 19, Sayre Kos, Senior Editor at Flexible Packaging Magazines, stops by to do a feature on our green energy efforts.

Sayre capturing some of the work in
progress. The feature is in the April
issue, available here.

March 26, additional, back-up supply and rejection wells are drilled.

 
 

Getting closer and closer! The heat exchangers are connected in early April.

The team from Kopar Industrial Services responsible for most of the hardware installation.

The stainless steel tanks are filters to remove sediments from the lines.

 

April 13, getting very close!

The system will be turned on, tested, and checked for leaks this week.

April 19, electric wiring of the controls starting this week...

...and is expected to take most of the week.

April 26. Water is pumped through the
system to check for leaks. Note the condensation on the pipes.

Of course, a few small leaks were found, but very few. Note the high-tech water collection system.

 

April 30th, one of our castlines has been connected to the system and we produced our first roll!

The film looked great and was approved by QC Manager Dan Acevedo (left) and operator Clemente Nevarez.

Dave Rohrschneider (COO) and Chris Rogers (VP Sales) coordinate the control system with Tony Ellis, our maintenance manager.

 

Perhaps the most amazing thing about this system is that this room-sized 340 ton chiller has been replaced by...

...this suitcase-sized heat exchanger!

Mid-May: The metallizer is connected to the system. Note the old pipes fitted to the new geo-pipes.

 

June 1st, all our extruders are
connected to the system. 

Early June, the presses are connected and the system is running in full "Auto Mode". Of course, plenty of tweaking still to do.

June 2nd, Ed Schock, Mayor of Elgin, comes to visit our plant and view the progress. 

 

Olle and the Mayor discussing the enormous potential of geothermal energy in our area. The Mayor is very supportive of small businesses, and promised to help promote our efforts. We greatly appreciate the support!

June 9th: Horizontal drilling! Rather than running piping from the 3rd supply well to the heat exchangers through the building, we simply drilled under it! Note the angled drill above right. To the right, the horizontal pipe is being connected to the well.

 

This saved us both time and money.

 

With the help of various adapters, we were able to re-use most of the existing piping from our old chiller system.

Stay tuned for
more updates!

       
       
       
     
       

Our Products | Our Capabilities | Sustainability | Quality | Industry Resources | Contact Us | Our Company | Careers | Site Map
1040 N. McLean Blvd., Elgin IL 60123 - Tel: 800-837-WRAP Fax: 847-695-7645  Email:
© 2010 Multifilm Packaging Corporation. Legal Disclaimer